Kyle Dunkerley
PIR-05 · Migration · April–May 2025

When the cutover changed.

I led outage planning, cutovers and health checks for a three-week Hyper-V to VMware migration.

Scope

21 VMs

Three physical hosts to two.

SQL server

3.5 TB

Total server storage across five drives.

The interruption

~6 hours on paper

Converter pre-scan locked the database at about 20%. The production application became unavailable.

Option 1 · Stop

An uncertain release

Lose scan progress with no guarantee the database lock releases.

Option 2 · DR

Reconcile later

New orders would need merging. The DBA identified a risk of missed orders.

Option 3 · Chosen together

Complete the migration.

With the site manager and DBA, we adjusted settings and continued. The service returned; skipping the re-scan shortened the overall process by about four hours.

  • Next: rebuilt two smaller database servers rather than converting them.